Toilet block update 29 April 2022

Trench in floor of toilet block shell.

It’s been a while since I’ve spotted anyone working at the toilet block. The original delay was because of Covid, and presumably that continues.

However, a trench has been dug across the floor recently, as the photo shows.

Just a reminder that back at the end of March the builder did advise:

The next steps will be
- sort trenching for the new plumbing in the toilet area.
- Set up for the new foundations, posts and floor to the BBQ area.
- There will be a few week where it seams not to much is being achieved. This is generally when the foundations are being sorted and if this is done incorrectly or rushed this will have massive implications on the rest of the project. Once the ground works are complete the rest should come together relatively quickly with a lot of visual progress.